Re: Large job advice It is really a simple math question. (Total number of shirts/Shirts per hour) * 2 sides.
A fully automatic press will take 167 hours to print 25K shirts. That is one month dedicated at 40 hrs a week and 300 shirts hour on 2 sides. If you are going to do this by hand and can do 50 shirts an hour at 2 sides you are looking at 1000 hours of time for 25K shirts which is 6.25 months at 40 hours a week. If you have that kind of time, go ahead.
For that volume, you can probably source it to China and get a good deal. There are also printers in the US that could do it for a higher cost than overseas.